Electric Vehicle Charge Stations
Project Start Date: Fall 2019
Construction Start Date: Fall 2024
Project Completion Date: Fall 2025
Project Description:
The Irvine Valley College Student Housing facility will be built on a previously undeveloped site on the southeast portion of campus near the Fine Arts Complex.
Access Control Project
Project Start Date: Spring 2019
Construction Start Date: Summer 2019
Project Completion Date: April 2022
Project Description:
The Access Control Project is a campus-wide security upgrade project. Its components, installed in two phases, include: Cameras and requisite software/servers/switches, Panic buttons, Keyless entry card readers with electronic access hardware/cabling/ADA barrier revisions, and an Automated system for Campus Police Dispatch.
Outdoor Learning Labs Project
Project Start Date: Spring 2021
Phase I Construction Start Date: July 2022
Phase I Construction End Date: August 2022
Phase II Construction Start Date: August 2022
Project Completion Date: December 2022
Live Oak Terrace Shade Structures Project
Project Start Date: Fall 2021
Construction Start Date: July 2022
Project Completion Date: November 2022
Project Description:
The Live Oak Terraces Shade Structure project will provide shading for the entire terrace seating area.
The project began Fall 2021. Estimated design approval by DSA is March 2022. Construction is slated to begin July 2022 with project completion November 2022.
Lot 6 – Solar Shade Project
Project Start Date: Fall 2020
Construction Start Date: February 2021
Project Completion Date: Fall 2021
Project Description:
Scheduled Maintenance Roofing and HVAC Project
Project Start Date: Fall 2021
Construction Start Date: Spring 2021
Project Completion Date: March 2022
Project Description:
The Scheduled Maintenance Roofing and HVAC Project is providing upgrades through repair and/or replacement of the roofing and HVAC systems of the PE 100, PE200, A100, A200 and A300 buildings.
Construction began Summer 2021 with an estimated completion January 2022. Due to supply chain delays, final project close out may extend into March 2022.
Campus-Wide Infrastructure Projects Plan
Project Start Date: Fall 2021 2021
Construction Start Date: Fall 2021
Project Completion Date: Ongoing
Project Description:
B Quad – ADA Transition Plan Project
Project Start Date: Fall 2020
Construction Start Date: July 2021
Project Completion Date: March 2022
Project Description:
The B Quad is getting a much needed facelift thanks to the District-Wide ADA Transition Plan Project. The project is occurring simultaneously at both campuses and consists of: Renovation of restrooms, replacement of sidewalks to make them ADA compliant, and new ADA compliant ramps, stairs and plaza areas. B Quad is one such plaza area.