Lot 6 – Solar Shade Project
Project Start Date: Fall 2020
Construction Start Date: February 2021
Project Completion Date: Fall 2021
Project Description:
Project Start Date: Fall 2020
Construction Start Date: February 2021
Project Completion Date: Fall 2021
Project Description:
Project Start Date: Fall 2021
Construction Start Date: Spring 2021
Project Completion Date: March 2022
Project Description:
The Scheduled Maintenance Roofing and HVAC Project is providing upgrades through repair and/or replacement of the roofing and HVAC systems of the PE 100, PE200, A100, A200 and A300 buildings.
Construction began Summer 2021 with an estimated completion January 2022. Due to supply chain delays, final project close out may extend into March 2022.
Project Start Date: Fall 2021 2021
Construction Start Date: Fall 2021
Project Completion Date: Ongoing
Project Description:
Project Start Date: Fall 2020
Construction Start Date: July 2021
Project Completion Date: March 2022
Project Description:
The B Quad is getting a much needed facelift thanks to the District-Wide ADA Transition Plan Project. The project is occurring simultaneously at both campuses and consists of: Renovation of restrooms, replacement of sidewalks to make them ADA compliant, and new ADA compliant ramps, stairs and plaza areas. B Quad is one such plaza area.
Project Start Date: Spring 2021
Construction Start Date: Spring 2022
Project Completion Date: October 2022
Project Description:
The Campus-Wide Lighting Project is providing upgrades across campus of inefficient lighting and related controls with the intent to reduce energy usage, reduce operating costs, achieve greater control of lighting systems.
Design phase began Spring 2021 and construction is estimated to begin Spring 2022. Project completion is estimated for October 2022.
Start Date: Fall 2019
Construction Start Date: Summer 2020
Project Completion Date: Spring 2021
Project Description:
The B100 Scheduled Maintenance Roofing and HVAC Project provided complete removal and replacement the roofing and HVAC units on the B100 building.
The project began shortly before campus shutdown in Fall 2019. Construction began Summer 2020 and completed Spring 2021.
Project Start Date: Fall 2019
Construction Start Date: Fall 2021
Projected Project Completion Date: Fall 2023
Tentative Enrollment Date: Spring 2024
Project Description:
Project Start Date: Fall 2021
Construction Start Date: Summer 2026
Project Completion Date: Summer 2027
Project Description:
The Student-Focused Campuswide Signage Implementation Project at Irvine Valley College (IVC) will create a comprehensive, campuswide wayfinding system to improve navigation, communication, and campus identity. The new signage will be clear, accessible, and student-centered, helping everyone move confidently across campus.
Key project components include: