Arts Village

Project Start Date: Fall 2019
Construction Start Date: Fall 2021
Projected Project Completion Date: Fall 2023
Tentative Enrollment Date: Spring 2024
Project Description:
 

Campus Wide Signage Project

Project Start Date: Fall 2021
Construction Start Date: Summer 2026
Project Completion Date: Summer 2027
Project Description:
The Student-Focused Campuswide Signage Implementation Project at Irvine Valley College (IVC) will create a comprehensive, campuswide wayfinding system to improve navigation, communication, and campus identity. The new signage will be clear, accessible, and student-centered, helping everyone move confidently across campus.

Key project components include:

Scheduled Maintenance Campus-Wide Painting Project

Project Start Date: Ongoing
Construction Start Date: Ongoing
Project Completion Date: Ongoing
Project Description:
The Scheduled Maintenance Campus-Wide Painting Project is a campus wide project aimed at painting and refreshing all buildings on campus.

Work is ongoing with this project with no set timeline for completion. Currently completed building painting projects include PE100, PE200 and M500.

IVC Facilities Projects Updates: April 19, 2021

Electronic Access Control

  • Liberal Arts completed
  • Library completed
  • PAC completed
  • LSB (B400) completed
  • A200 completed
  • SSC & B100 completed
  • BSTIC Completed
  • A100 completed
  • B200 Completed
  • All remaining buildings will continue to transition over to the new electronic access according to the agreed prioritized list: Currently in progress: B300, A300, PE100, PE200
  • Estimated completion: September 2021

B200 Chemistry Lab Renovation: Years 1-3

B200 Chemist

B 200 Furniture Fixtures Equipment (FFE) and Finishes Renovations Project

Project Start Date: Spring 2020
Construction Start Date: August 2021
Project Completion Date: December 2021
Project Description:
The B200 Furniture, Fixtures, Equipment (FFE) and Finishes Renovations Project will provide a much needed facelift to the B200 building. From classrooms to offices to shared open spaces, all areas of the B200 is getting some much needed TLC.

PE 200 Gas Generator Project

Project Start Date: Fall 2021
Construction Start Date: April 2022
Project Completion Date: September 2022
Project Description:
The PE 200 Gas Generator Project will provide a continuous source of electricity for the PE 200 building.

The project is still in design with contractor selection February 2022. Construction will begin April 2022, and project completion September 2022.