Campus-Wide Lighting Upgrades Project

Project Start Date: Spring 2021
Construction Start Date: Spring 2022
Project Completion Date: October 2022
Project Description:
The Campus-Wide Lighting Project is providing upgrades across campus of inefficient lighting and related controls with the intent to reduce energy usage, reduce operating costs, achieve greater control of lighting systems.

Design phase began Spring 2021 and construction is estimated to begin Spring 2022. Project completion is estimated for October 2022.

Arts Village

Project Start Date: Fall 2019
Construction Start Date: Fall 2021
Projected Project Completion Date: Fall 2023
Tentative Enrollment Date: Spring 2024
Project Description:
 

Campus Wide Signage Project

Project Start Date: Fall 2021
Construction Start Date: Summer 2026
Project Completion Date: Summer 2027
Project Description:
The Student-Focused Campuswide Signage Implementation Project at Irvine Valley College (IVC) will create a comprehensive, campuswide wayfinding system to improve navigation, communication, and campus identity. The new signage will be clear, accessible, and student-centered, helping everyone move confidently across campus.

Key project components include:

Scheduled Maintenance Campus-Wide Painting Project

Project Start Date: Ongoing
Construction Start Date: Ongoing
Project Completion Date: Ongoing
Project Description:
The Scheduled Maintenance Campus-Wide Painting Project is a campus wide project aimed at painting and refreshing all buildings on campus.

Work is ongoing with this project with no set timeline for completion. Currently completed building painting projects include PE100, PE200 and M500.

IVC Facilities Projects Updates: April 19, 2021

Electronic Access Control

  • Liberal Arts completed
  • Library completed
  • PAC completed
  • LSB (B400) completed
  • A200 completed
  • SSC & B100 completed
  • BSTIC Completed
  • A100 completed
  • B200 Completed
  • All remaining buildings will continue to transition over to the new electronic access according to the agreed prioritized list: Currently in progress: B300, A300, PE100, PE200
  • Estimated completion: September 2021

B200 Chemistry Lab Renovation: Years 1-3

B200 Chemist

B 200 Furniture Fixtures Equipment (FFE) and Finishes Renovations Project

Project Start Date: Spring 2020
Construction Start Date: August 2021
Project Completion Date: December 2021
Project Description:
The B200 Furniture, Fixtures, Equipment (FFE) and Finishes Renovations Project will provide a much needed facelift to the B200 building. From classrooms to offices to shared open spaces, all areas of the B200 is getting some much needed TLC.