B Quad – ADA Transition Plan Project
Project Start Date: Fall 2020
Construction Start Date: July 2021
Project Completion Date: March 2022
Project Description:
The B Quad is getting a much needed facelift thanks to the District-Wide ADA Transition Plan Project. The project is occurring simultaneously at both campuses and consists of: Renovation of restrooms, replacement of sidewalks to make them ADA compliant, and new ADA compliant ramps, stairs and plaza areas. B Quad is one such plaza area.
Campus-Wide Lighting Upgrades Project
Project Start Date: Spring 2021
Construction Start Date: Spring 2022
Project Completion Date: October 2022
Project Description:
The Campus-Wide Lighting Project is providing upgrades across campus of inefficient lighting and related controls with the intent to reduce energy usage, reduce operating costs, achieve greater control of lighting systems.
Design phase began Spring 2021 and construction is estimated to begin Spring 2022. Project completion is estimated for October 2022.
Scheduled Maintenance Roofing and HVAC Project
Start Date: Fall 2019
Construction Start Date: Summer 2020
Project Completion Date: Spring 2021
Project Description:
The B100 Scheduled Maintenance Roofing and HVAC Project provided complete removal and replacement the roofing and HVAC units on the B100 building.
The project began shortly before campus shutdown in Fall 2019. Construction began Summer 2020 and completed Spring 2021.
Arts Village
Project Start Date: Fall 2019
Construction Start Date: Fall 2021
Projected Project Completion Date: Fall 2023
Tentative Enrollment Date: Spring 2024
Project Description:
Campus Wide Signage Project
Project Start Date: Fall 2021
Construction Start Date: Summer 2026
Project Completion Date: Summer 2027
Project Description:
The Student-Focused Campuswide Signage Implementation Project at Irvine Valley College (IVC) will create a comprehensive, campuswide wayfinding system to improve navigation, communication, and campus identity. The new signage will be clear, accessible, and student-centered, helping everyone move confidently across campus.
Key project components include:
Scheduled Maintenance Campus-Wide Painting Project
Project Start Date: Ongoing
Construction Start Date: Ongoing
Project Completion Date: Ongoing
Project Description:
The Scheduled Maintenance Campus-Wide Painting Project is a campus wide project aimed at painting and refreshing all buildings on campus.
Work is ongoing with this project with no set timeline for completion. Currently completed building painting projects include PE100, PE200 and M500.
Soccer, Baseball and Practice Fields Project
Project Start Date: Summer 2019
Construction Start Date: March 2021
Project Completion Date: Summer 2022
Project Description:
Scheduled Maintenance Campus-Wide Floors and Finishes Project
Project Start Date: Ongoing
Construction Start Date: Ongoing
Project Completion Date: Ongoing
Project Description:
The Scheduled Maintenance Campus-Wide Floors and Finishes Project is removing, replacing and or refinishing flooring in classrooms, hallways and common areas across campus.
Work is ongoing with this project with no set timeline for completion.