Student Union
Project Start Date: Fall 2019
Construction Start Date: 2024
Project Completion Date: 2026‐2027
Gross Square Footage: 31,300 sf
Assignable Square Footage: 30,362 sf
Project Description:
Project Start Date: Fall 2019
Construction Start Date: 2024
Project Completion Date: 2026‐2027
Gross Square Footage: 31,300 sf
Assignable Square Footage: 30,362 sf
Project Description:
Project Start Date: Fall 2018
Phase I Construction Start Date: June 2019
Phase I Construction Completion Date: November 2019
Phase II Construction Start Date: March 2020
Phase II Construction Completion Date: December 2020
Phase III Construction Start Date: March 2021
Phase III Construction End Date: August 2021
Project Completion Date: Summer 2021
Project Start Date: Fall 2021
Construction Start Date: Summer 2025
Project Completion Date: February 2026 (early Spring 2026)
Project Description:
The Scheduled Maintenance Campus-Wide Electrical Upgrades Project is providing upgrades to electrical breakers and switch gear across campus.
Replacement of electrical infrastructure equipment is currently underway with construction completion estimate for December 2025.
Project Design Start Date: Spring 2020
Construction Start Date: March 2022
Project Completion Date: August 2022 (Confirmed supply chain delays)
Project Description:
The campus’ Fire Alarm System is getting campus wide upgrades to the system panels and sensors. The project was delayed due to campus shutdown and was started back up in 2021.
Due to supply chain delays, the project’s construction start date has been pushed forward to March 2022 with a new estimated completion date of August 2022.
Project Start Date: 2024-2025
Construction Start Date: 2027-2028
Project Completion Date: TBD
Project Description:
The A 200 Success Center is a potential candidate for state funding. The Initial Project Proposal (IPP) will be submitted to the State Chancellor’s office July 2021.
Estimated timeline if approved would have the preliminary design phase beginning as early as 2024 and construction starting as soon as 2027.
Project Start Date: Fall 2019
Construction Start Date: 2024
Project Completion Date: 2026-2027
Building Gross Square Footage: 54,000 sf
Assignable Square Footage: 47,437 sf
Project Description:
The Student Services building will be built on the footprint of the current B-100 building.
Project Start Date: Fall 2021
Construction Start Date: November 2022
Project Completion Date: March 2023
Project Description:
The Satellite Coffee Structures at IVC and ATEP and Cafeteria Upgrades at IVC Project consists of IVC cafeteria upgrades, a new permanent structure at IVC close to the new Art Village (under construction), mobile food stands, as well as perishable food and coffee vending equipment at IDEA on the ATEP satellite campus.
CAPITAL IMPROVEMENT COMMITTEE (CIC): New building construction (capital improvement) and/or improvements (scheduled maintenance) to existing buildings and grounds.
Project Start Date: Spring 2020
Construction Start Date: Summer 2024
Completion Date: Fall 2025
Project Description:
The Library Renovation Project at Irvine Valley College (IVC) delivers a fully upgraded, student-centered library that blends comfort, accessibility, and functionality. Spanning multiple phases, the project enhances both the building’s interior and exterior, modernizes its systems, and expands spaces to better support academic success and community connection.
Key improvements include: