Gym Bleachers Replacement Project

Project Start Date: Fall 2020
Construction Start Date: August 2021
Project Completion Date: April 2022 (Confirmed Supply chain delays)
Project Description:
The Gym Bleachers Replacement Project includes replacement of the telescoping bleacher system, upgrades to the existing fire alarm system in the PE200 building, and accessibility upgrades including: accessible entrances, drinking fountain/bottle fill stations, signage, restrooms and parking modifications.

Student Union

Project Start Date: Fall 2019
Construction Start Date: 2024
Project Completion Date: 2026‐2027
Gross Square Footage: 31,300 sf
Assignable Square Footage: 30,362 sf
Project Description:

B 200 Chemistry Labs Renovation

Project Start Date: Fall 2018
Phase I Construction Start Date: June 2019
Phase I Construction Completion Date: November 2019
Phase II Construction Start Date: March 2020
Phase II Construction Completion Date: December 2020
Phase III Construction Start Date: March 2021
Phase III Construction End Date: August 2021
Project Completion Date: Summer 2021

Scheduled Maintenance Campus-Wide Electrical Upgrades Project

Project Start Date: Fall 2021
Construction Start Date: Summer 2025
Project Completion Date: December 2025
Project Description: 
The Scheduled Maintenance Campus-Wide Electrical Upgrades Project is providing upgrades to electrical breakers and switch gear across campus.

Replacement of electrical infrastructure equipment is currently underway with construction completion estimate for December 2025.

Campus-Wide Fire Alarm Controller Upgrades Project

Project Design Start Date: Spring 2020
Construction Start Date: March 2022
Project Completion Date: August 2022 (Confirmed supply chain delays)
Project Description:

The campus’ Fire Alarm System is getting campus wide upgrades to the system panels and sensors. The project was delayed due to campus shutdown and was started back up in 2021.

Due to supply chain delays, the project’s construction start date has been pushed forward to March 2022 with a new estimated completion date of August 2022.

English Language Center (A 200 Success Center)

Project Start Date: 2024-2025
Construction Start Date: 2027-2028
Project Completion Date: TBD
Project Description:

The A 200 Success Center is a potential candidate for state funding. The Initial Project Proposal (IPP) will be submitted to the State Chancellor’s office July 2021.

Estimated timeline if approved would have the preliminary design phase beginning as early as 2024 and construction starting as soon as 2027.

Student Services Center

Project Start Date: Fall 2019
Construction Start Date: 2024
Project Completion Date: 2026-2027
Building Gross Square Footage: 54,000 sf
Assignable Square Footage: 47,437 sf 
Project Description:
The Student Services building will be built on the footprint of the current B-100 building. 

Satellite Coffee Structures at IVC and ATEP and Cafeteria Upgrades at IVC Project

Project Start Date: Fall 2021
Construction Start Date: November 2022
Project Completion Date: March 2023
Project Description:
The Satellite Coffee Structures at IVC and ATEP and Cafeteria Upgrades at IVC Project consists of IVC cafeteria upgrades, a new permanent structure at IVC close to the new Art Village (under construction), mobile food stands, as well as perishable food and coffee vending equipment at IDEA on the ATEP satellite campus.