Fire Alarm Controller Upgrades

Fire Alarm Controller Upgrades
4/19/2021 Update:

  • Agreement for Architectural Services awarded to SVA Architects
  • Estimated DSA Submittal: June 2021
  • Estimated DSA Approval: August 2021
  • Construction Bidder will be selected: September 2021
  • Submit to October Board
  • Construction Start: November 2021
  • Estimated Completion: February 2021